  • Question
  • If m men working m h per day, can do m units of work in m days, then n men working n h per day would be able to complete how units of work in days?


  • Options
  • A. n3/m2
  • B. m3/n2
  • C. m4/n2
  • D. n4/m3

  • Correct Answer
  • n3/m2 

    Explanation

    Let the required number of units of work = k
    According to the formula,
    W1= m and W2 = k
    M1T1D1W2 = M2T2D2W1
    ? m x m x m x k = n x n x n x m
    ? x= (m x n3) / m3 = n3/m2


  • Time and Work problems


    Search Results


    • 1. 
      40 men can build a wall 200 m long in 12 days, working 8h a day. What will be the number of days that 30 men will take to built a similar wall 300 m long, working 6h per days.

    • Options
    • A. 32
    • B. 18
    • C. 36
    • D. 9
    • Discuss
    • 2. 
      20 men can cut 30 tree in 4 h. If 4 men leave the job, how many trees will be cut in 12 h?

    • Options
    • A. 72
    • B. 80
    • C. 68
    • D. 79
    • Discuss
    • 3. 
      12 men can do a piece of work in 24 days. How many days are needed to go complete the work, if 8 men do this work?

    • Options
    • A. 28
    • B. 36
    • C. 48
    • D. 52
    • Discuss
    • 4. 
      20 women can complete apiece of work in 7 day. If 8 more women are put on the job. In how many days will they complete the work?

    • Options
    • A. 4.5 days
    • B. 5 days
    • C. 5.5 days
    • D. 4.5 days
    • Discuss
    • 5. 
      A and B can do a piece of work in 60 days and 75 days, respectively. Both begin together but after a certain time A leaves off. In such case B finishes the remaining work in 30 days. After how many days did A leave?

    • Options
    • A. 25 days
    • B. 21 days
    • C. 20 days
    • D. 24 days
    • Discuss
    • 6. 
      20 men complete one-third of a work in 20 days. How many more men should be employed to finished the rest of work in 25 more days.?

    • Options
    • A. 15
    • B. 12
    • C. 18
    • D. 25
    • Discuss
    • 7. 
      45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to the employed will be?

    • Options
    • A. 50
    • B. 54
    • C. 60
    • D. 72
    • Discuss
    • 8. 
      If 3 men or 4 women can built a wall in 43 days, in how many days can 7 men and 5 women build this wall?

    • Options
    • A. 16 days
    • B. 25 days
    • C. 21 days
    • D. 12 days
    • Discuss
    • 9. 
      A and B can do a piece of work in 18 days. B and C in 24 days, C and A in 36 days. Find the time in which A, B and C working together can finish the work.

    • Options
    • A. 8
    • B. 16
    • C. 24
    • D. 36
    • Discuss
    • 10. 
      A and B can do a piece of work in 72 days. B and C can do it in 120 days, A and C and do it in 90 days. In what time can A alone do it?

    • Options
    • A. 80 days
    • B. 100 days
    • C. 120 days
    • D. 150 days
    • Discuss


    Comments

    There are no comments.

Enter a new Comment