Pick up the correct definition from the following:
Options
A. The lateral pressure exerted by the soil when the retaining wall moves away from the back fill, is generally known as active earth pressure of the soil
B. The lateral pressure exerted by the soil when the retaining wail moves towards the soil, is generally known as 'Passive earth pressure of the soil'
C. The lateral pressure exerted by the soil when the retaining wall has no movement relative to the back fill, is known as 'earth pressure at rest of the soil'
D. All the above.
Correct Answer
All the above.
More questions
1. Pick up the correct statement from the following :
Options
A. an observation or the resulting reading with the level on a levelling staff is called sight
B. a back sight is the first sight taken after setting up the instrument in any position
C. the first sight on each change point is a fore sight
D. the second sight on each change point is a back sight
Correct Answer: initial cost of construction is low
5. If S, L and R are the arc length, long chord and radius of the sliding circle then the perpendicular distance of the line of the resultant cohesive force, is given by