  • A project charter is one of the key deliverables to come from the initiation process. The project charter should by issued by


  • Options
  • A. one or more functional managers
  • B. The head of the performing organization
  • C. A manager external to the project
  • D. The CFO

  • Correct Answer
  • A manager external to the project 

    Explanation

    The other answers could be accurate in specific situations, but their role alone does not meet the keyb criterion of being "external" to the project team. Answers A, B, and D are incorrect because these individuals are not external to the project.


  • PMP Certification problems


    Search Results


    • 1. Sometimes project managers forget all of the expenses that they can incur on a project, such as capital resources and assets. This can have an impact upon their budgets and the economic return on the project. A cost that has been incurred and cannot be reversed is known as a

    • Options
    • A. Fixed Cost
    • B. Direct Cost
    • C. Variable Cost
    • D. Sunk Cost
    • Discuss
    • 2. The payback period can become an important issue when a large scope project is developed over several years. Maureen has been assigned the responsibility of calculating the payback period for her project that is to be completede in 3 years. The internal rate of return(IRR) is 7% and the annual savings will be $800,000 per year. The total cost is $4,000,000 and the rate of return during this time period is 3%. What is the payback period of Maureen's project?

    • Options
    • A. 3 years
    • B. 4 years
    • C. 5 years
    • D. 13.3 years
    • Discuss
    • 3. One of the goals of management by objectives (MBO) is to ensure that objectives of one level within an organization are supportive of and aligned with the objectives of another level of the organization. This methodology has been popular within some organizations as they define their culture. Which of the following is not true about MBO?

    • Options
    • A. It has a top-down orientation
    • B. Corrective actions are not part of the process
    • C. You need to establish clear and achievable objectives
    • D. MBO is a natural fit for Project Management
    • Discuss
    • 4. You have started your own company based upon PMI methodologies and have been contracted by the government to develope a new interface for one of its computer applications. You develope a solution and win the bid for the contract but encounter problems at the end of the project when the customer says that you did not fullfill their needs. You are throughly shocked. What is your conclusion of the situation?

    • Options
    • A. There are always more customers available
    • B. If the customer is not satisfied, the project is not successful
    • C. Change control management was not effective
    • D. The customer did not communicate very well
    • Discuss
    • 5. The software development life cycle begins with a proof of concept and progress into the build, test, and acceptance phases as the project develops. Some times, differences between stakeholders can develop into conflict, which impacts the customer. As a trained, professional project manager, how do you handle this situation and resolve the customer's concerns?

    • Options
    • A. Let the customer vent and take notes
    • B. Schedule a meeting
    • C. Develope a change request for the customer
    • D. Resolve the matter in favour of the customer
    • Discuss
    • 6. You are a project manager for the redevelopment of the Hoover Dam. Your team has been provided with the scope statement, but it lacks many description details. Your team is concerned because the project is in the initiation phase and it wants to postpone it until it has more information. As the project manager, you recommend that

    • Options
    • A. The team should go forward, but be caution about the lack of details and the impact upon the timeline for the project
    • B. The project should not go forward until the stakeholders agree about the scope and purpose of the project
    • C. The team should verify the scope and realize that more details will be available as more project characteristics are progressively elaborated.
    • D. The team should review the project selection criteria for the Hoover Dam project
    • Discuss
    • 7. A Good CFO will tell you that it is important to look at your bottom line and determine how to increase profits for the organization. Veronica, the new CFO at a local university, is taking that approach and applying it to new projects. Therefore,she wants to include costs from each phase of the project on a total expenditure is known as

    • Options
    • A. An opportunity cost
    • B. A sunk cost
    • C. NPV
    • D. A life cycle
    • Discuss
    • 8. You are working on a new project to develop a new wireless product with ease - of - use features recommended by customers. It is as yet undetermined which features and the extent to which each feature will be incorporated into the product.You have a focus group that will continue to evaluate the features as the project goes forward.The focus group is authorized to suggest changes, as are your engineers and the quality department.As a project manager, what will help you most to minimize the effect of these changes?

    • Options
    • A. A change management plan
    • B. A scope management plan
    • C. Do not continue with the project until all of the features are clearly defined in the scope statement and scope definition.
    • D. This is an expected part of every project. A good project manager will have a communications plan in place to be sure everyone knows what is happening on the project.
    • Discuss
    • 9. On a systems development project, Richard needs two programmers. He knows John and Smith were able to create a program in 40 days similar to the one he wants to create on his project. He decides to use 40 days as his estimate. This is an example of what type of estimating?

    • Options
    • A. Parametric modeling
    • B. Analogous
    • C. Rule of thumb
    • D. Fixed Rate
    • Discuss
    • 10. Iam looking to estimate the cost on a project, but I don't want to spend a lot of time on a detailed analysis. I really want a ballpark figure. What options do I have?

    • Options
    • A. None - Cost estimating requires details to be accurate
    • B. Use the cost of similar projects
    • C. Use a rule-of-thumb or per-square-foot estimate
    • D. Add up the costs on the WBS
    • Discuss