Correct Answer: I Inputs Project scope statement Work breakdown structure WBS dictionary Activity cost estimates Activity cost estimate supporting detail Project schedule Resource calendars Contract Cost management plan II Tools and Techniques Cost aggregation Reserve analysis Parametric estimating Funding limit reconciliation III Outputs Cost baseline Project funding requirements Cost management plan (updates) Requested changes