logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • The ratio of efficiencies of P, Q and R is 2 : 3 : 4. While P and R work on alternate days and Q work for all days. Now the work completed in total 10 days and the total amount they get is Rs. 1200. Find the amount of each person(respectively).


  • Options
  • A. 200, 600, 400
  • B. 400, 600, 200
  • C. 600, 200, 400
  • D. 400, 200, 600

  • Correct Answer
  • 200, 600, 400 

    Explanation

    Ratio of efficiencies of P, Q and R = 2 : 3 : 4

    From the given data,

    Number of working days of P, Q, R = 5 : 10 : 5

    Hence, ratio of amount of p, Q, R = 2x5 : 3x10 : 4x5 = 10 : 30 : 20

    Amounts of P, Q, R = 200, 600 and 400.

  • Tags: AIEEE, Bank Exams, CAT, GATE, Analyst, Bank Clerk, Bank PO

    Time and Work problems


    Search Results


    • 1. Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing 1/3 of the task. Then, Sharan takes over and completees the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayuk' had worked faster than Sharan ?

    • Options
    • A. 24
    • B. 45
    • C. 72
    • D. 30
    • Discuss
    • 2. Lasya alone can do a work in 16 days. Srimukhi?s efficiency is 20 % lesser than that of Laya. If Rashmi and Srimukhi together can do the same work in 12 days, then find the efficiency ratio of Rashmi to that of Lasya?

    • Options
    • A. 19 : 7
    • B. 30 : 19
    • C. 8 : 15
    • D. 31 : 17
    • Discuss
    • 3. A, B and C can do a piece of work in 72, 48 and 36 days respectively. For first p/2 days, A & B work together and for next ((p+6))/3days all three worked together. Remaining 125/3% of work is completed by D in 10 days. If C & D worked together for p day then, what portion of work will be remained?

    • Options
    • A. 1/5
    • B. 1/6
    • C. 1/7
    • D. 1/8
    • Discuss
    • 4. Amar can do a piece of work in 10 days. He works at it for 4 days and then Arun finishes it in 9 days. In how many days can Amar and Arun together finish the work ?

    • Options
    • A. 4 days
    • B. 8 days
    • C. 3 days
    • D. 6 days
    • Discuss
    • 5. Five men and nine women can do a piece of work in 10 days. Six men and twelve women can do the same work in 8 days. In how many days can three men and three women do the work ?

    • Options
    • A. 18 days
    • B. 20 days
    • C. 16 days
    • D. 14 days
    • Discuss
    • 6. A town having teenagers(boys & girls) of 5000 requires 150 litre of water per head. It has a tank measuring 20 m × 15 m × 5 m. The water of this tank will sufficient for ____ days.

    • Options
    • A. 8
    • B. 6
    • C. 4
    • D. 2
    • Discuss
    • 7. Mr. stenley employed a certain number of typist for his project. 8 days later 20% of the typist left the job and it was found that it took as much time to complete the rest work from then as the entire work needed with all the employed typists. The average speed of a typist is 20 pages/hour. Minimum how many typist could be employed?

    • Options
    • A. 10
    • B. 5
    • C. 15
    • D. 4
    • Discuss
    • 8. 5 men and 3 boys can together cultivate a 23 acre field in 4 days and 3 men and 2 boys together can cultivate a 7 acre field in 2 days. How many boys will be needed together with 7 men, if they cultivate 45 acre of field in 6 days.

    • Options
    • A. 6
    • B. 4
    • C. 2
    • D. 3
    • Discuss
    • 9. Raghu can complete a work in 12days working 9 hours a day. Arun can complete the same work in 8 days working 11 hours a day. If both Raghu and Arun work together, working 12 hours a day, in how many days can they complete the work ? A) 3449 days B) 12449 days C) 4349 days D) 41249 days

    • Options
    • A. Option A
    • B. Option B
    • C. Option C
    • D. Option D
    • Discuss
    • 10. Prabhas is twice as good a workman as Rana and finishes a piece of work in 3 hours. In how many hours they together could finish that piece of work?

    • Options
    • A. 3 hrs
    • B. 3.5 hrs
    • C. 2.5 hrs
    • D. 2 hrs
    • Discuss


    Comments

    There are no comments.

Enter a new Comment