  • Question
  • A contractor undertook a project to complete it in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that he needed to increase 5 additional men every 2 days to complete the work in the time the client wanted it: If the work was further increased by 50% but the contractor continues to increase the 5 workers o every 2 days then how many more days are required over the initial time specified by the client.


  • Options
  • A. 1 day
  • B. 2 days
  • C. 5 days
  • D. None of these

  • Correct Answer
  • 2 days 

    Explanation

    Total work = 100+50 = 150man-days

    In 8 days 100 man-days work  has been completed. Now on 9th and 10th day there will be 25 workers. So in 2 days they wll complete additional 50 man- days work. Thus the work requires 2 more days.


  • Time and Work problems


    Search Results


    • 1. Three athletes can complete one round around a circular field in 16, 24 and 36 min respectively. They start running together at same instant then after how much time they will meet to each other for first time ?

    • Options
    • A. 2 hrs 24 min
    • B. 2 hrs 44 min
    • C. 1 hrs 24 min
    • D. 1 hrs 24 min
    • Discuss
    • 2. A contractor undertake to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged so that the work may finish in time ?

    • Options
    • A. 64
    • B. 62
    • C. 58
    • D. 56
    • Discuss
    • 3. 9 men and 12 boys finish a job in 12 days, 12 men and 12 boys finish it in 10 days. 10 men and 10 boys shall finish it in how many days ?

    • Options
    • A. 15 days
    • B. 11 days
    • C. 14 days
    • D. 12 days
    • Discuss
    • 4. P is 30% more efficient than Q. How much time will they, working together, take to complete a job which P alone could have done in 23 days?

    • Options
    • A. 16 days
    • B. 13 days
    • C. 15 days
    • D. 12 days
    • Discuss
    • 5. Four pipes P,Q, R and S can fill a cistern in 20,25, 40 and 50 hours respectively.The first pipe P was opened at 6:00 am, Q at 8:00 am, R at 9:00 am and S at 10:00 am. when will the Cistern be full?

    • Options
    • A. 4:18 pm
    • B. 3:09 pm
    • C. 12:15 pm
    • D. 11:09 am
    • Discuss
    • 6. A can build a wall in 16 days while B can destroy it in 8 days. A worked for 5 days. Then B joined with A for the next 2 days. Find in how many days could A build the remaining wall ?

    • Options
    • A. 12 days
    • B. 14 days
    • C. 13 days
    • D. 16 days
    • Discuss
    • 7. A and B can do a piece of work for Rs 1540. Find the difference between the wages of C and B for the same work If A can do the work in 12 days and B can do the same work in 8 days and with the help of C, A and B can do the same work in 2 days?

    • Options
    • A. 980
    • B. 1232
    • C. 810
    • D. 1121
    • Discuss
    • 8. Time taken by P alone to finish a work is 50% more than the time taken by P and Q together. Q is thrice as efficient as R. If Q and R together can complete the work in 22.5 days, then how many days will P alone take to complete the work ?

    • Options
    • A. 17 days
    • B. 11 days
    • C. 15 days
    • D. 16 days
    • Discuss
    • 9. P can do a piece of work in 5 less days than Q. If both of them can do the same work in 1119 days, in how many days will Q alone do the same work ?

    • Options
    • A. 24 days
    • B. 25 days
    • C. 20 days
    • D. 19 days
    • Discuss
    • 10. X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?

    • Options
    • A. 1/3
    • B. 2/3
    • C. 1/6
    • D. 5/6
    • Discuss