A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men?
Aptitude
Chain Rule
Difficulty: Medium
Choose an option
-
A1
-
B$1 \frac{1}{4}$
-
C$1 \frac{3}{4}$
-
D$1 \frac{1}{2}$
Answer
Correct Answer: 1
Explanation
### Concept & Man-Days Equivalence
The total amount of work in a project can be quantified as the total sum of "man-days" (the number of workers multiplied by the number of days they worked).
$$ \text{Total Work} = (M_1 \times D_1) + (M_2 \times D_2) $$
### Step-by-Step Solution
1. **Calculate the actual total man-days required:**
- Initial phase: 30 men worked for 25 days. ($30 \times 25 = 750$ man-days)
- Final phase: 5 more men joined ($30 + 5 = 35$ men). The work finished "one day earlier" than the planned 38 days, meaning the total project took 37 days.
- The final phase lasted $37 - 25 = 12$ days.
- Work completed in final phase: $35 \times 12 = 420$ man-days.
- Total work = $750 + 420 = 1170$ man-days.
2. **Calculate the hypothetical time for the original crew:**
- If only the original 30 men worked the whole time, the total days required would be:
- $\text{Days} = \frac{\text{Total Work}}{\text{Men}} = \frac{1170}{30} = 39$ days.
3. **Determine the delay:**
- The planned deadline was 38 days.
- Actual time taken by the original 30 men would be 39 days.
- Delay = $39 - 38 = 1$ day.
### Exam Strategy & Shortcut
Focus entirely on the remaining work after 25 days.
The remaining work was successfully completed by 35 men in 12 days ($35 \times 12 = 420$ units).
If the original 30 men had done this remaining work, they would have taken $\frac{420}{30} = 14$ days.
The total time would have been $25 \text{ (initial)} + 14 \text{ (remaining)} = 39$ days.
Since the deadline was 38 days, the contractor would simply be $39 - 38 = 1$ day behind.
### Common Pitfall
Miscalculating the duration of the second phase. "Finished one day earlier" refers to the original 38-day estimate, making the total project duration 37 days, not meaning 37 days for the second phase alone.
### Final Answer
Therefore, the correct answer is **1**.