Pick up the method of surveying in which field observations and plotting proceed simultaneously from the following
chain surveying
compass surveying
plan table surveying
tacheometric surveying.
Correct Answer:
plan table surveying
← Previous Question
Next Question→
More Questions from
Surveying
The most reliable method of plotting a theodolite traverse, is
If h is the difference in level between end points separated by l, then the slope correction is . The second term may be neglected if the value of h in a 20 m distance is less than
The radius of curvature of the arc of the bubble tube is generally kept
If θ is the slope of the ground and l is the measured distance, the correction is
For true difference in elevations between two points A and B, the level must be set up
Pick up the correct statement from the following:
If L is the perimeter of a closed traverse, ΔD is the closing error in departure, the correction for the departure of a traverse side of length l, according to Bowditch rule, is
For a closed traverse the omitted measurements may be calculated
Pick up the correct statement from the following :
The sensitiveness of a level tube decreases if
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments