Difficulty: Easy
Correct Answer: Architect/engineer
Explanation:
Introduction / Context:
Early-stage estimates guide feasibility and funding decisions when design information is limited. These are order-of-magnitude and conceptual budgets that rely on parametric data, historical cost indices, and schematic take-offs. Assigning responsibility clarifies who should supply the assumptions behind the numbers.
Given Data / Assumptions:
Concept / Approach:
In typical building projects, the architect/engineer (A/E) prepares preliminary and conceptual estimates tied to the evolving design, often validated by a quantity surveyor or cost consultant. A construction manager may also produce estimates in CM-at-risk or early contractor involvement models, but in traditional delivery, the A/E leads at this stage in coordination with the owner.
Step-by-Step Solution:
Identify which role has design custody and access to scope assumptions at concept level: the A/E.Acknowledge that CMs contribute when engaged early, but question expects the conventional answer.Select “Architect/engineer”.
Verification / Alternative check:
Standard practice guides indicate the A/E or a cost consultant under the A/E team prepares Class 4–5 estimates (conceptual), with owner approvals following.
Why Other Options Are Wrong:
Construction manager: feasible under certain delivery methods, but not universally the default.Owner alone: lacks the technical detail and benchmarks without A/E support.None of these: incorrect because A/E is a recognized preparer.
Common Pitfalls:
Final Answer:
Architect/engineer
Discussion & Comments