Project Integration Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Develop Project Charter phase?

Correct Answer: I Inputs Contract (when applicable) Project statement of work Enterprise environmental factors Organizational process assets II Tools and Techniques Project selection methods Project management methodology Project management information system Expert Judgment III Outputs 1 Project charter