Curioustab
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Home
»
Certification
»
PMP Certification
An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?
Additional resources using the contingency fund
Escalation approval to use contingency funding
Team overtime to meet schedule
Corrective action based on causes
Show Answer
Correct Answer:
Corrective action based on causes
← Previous
Next →
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment