Tushar takes 6 hours to complete a piece of work, while Amar completes the same work in 10 hours. If both of them work together, then what is the time required to complete the work?

Correct Answer: 3 hours 45 minutes

Explanation:

Let them take x hours working together


1/x = 1/10 + 1/6 = 8/30


X= 30/8 hours = 15/4 hours = 3 hours 45 minutes