A work can be completed by 28 women in 36 days. If 4 women leave after working for 18 days, then how many days will be needed to complete the remaining work?

Correct Answer: 21

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion