The rates of working of A and B are in the ratio 3 : 4. The number of days taken by them to finish the work are in the ratio?
3 : 4
9 : 16
4 : 3
None of these
Correct Answer:
4 : 3
Explanation:
Radio of times taken = (1/3) : (1/4) = 4 : 3
← Previous Question
Next Question→
More Questions from
Time and Work
A does half as much work as B in three-fourth of the time. If the together they take 18 days to complete a work. How much time shall B take to do it?
A and B together can do a work in 24 days. B alone does its 1/3 part in 12 days. How long will A alone take to do the remaining work?
15 men complete a work in 16 days If 24 men are employed then the time require to complete that work will be
A can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?
A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in?
Aarti can do a piece of work in 6 days. In how many days will she complete three time of work of same type?
A and B can do a piece of work in 6 and 12 days, respectively. They (both) will complete the work in how many days?
If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in?
'A' can do a piece of work in x days and B can do the same work 3x days. To finish the work together they take 12 days. What is the value of x?
X can completed a job in 12 days. If X and Y work together, they can complete the job in 6 2/ 3 days, Y alone can complete the job in
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments