A can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?

Correct Answer: 1/6

Explanation:

A's 1 day's work = 1/18
B's 1 day's work = 1/9
(A + B)'s 1 day's work = 1/9 + 1/18 = 3/18 = 1/6