Home » Aptitude » Time and Work

P alone can complete a piece of work in 6 days. Work done by Q alone in one day is equal to one-third of the work done by P alone in one day. In how many days can the work be completed if P and Q work together ?

Correct Answer: 4 (1/2)

Explanation:

Work done by P alone in one day = 1/6th of the total work done by Q alone in one day = 1/3(of that done by P in one day) = 1/3(1/6 of the total) = 1/18 of the total. 


 


Work done by P and Q, working together in one day = 1/6 + 1/18  = 4/18 = 2/9 


 


They would take 9/2 days = 4 (1/2) days to complete the work working together.


← Previous Question Next Question→

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion