A can do a work in 36 days and B in 12 days. If they work on it together, then in how many days will they be able to do the work?
8
6
10
9
Correct Answer:
9
← Previous Question
Next Question→
More Questions from
Time and Work
P can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how manydays, was the work completed?
Badki can bake 45 cakes in 9 hours, Badki and Chutki together can bake 80 cakes in 10 hours. How many cakes Chutki can bake in 40 hours?
Prabodh has done 1/2 of a job in 30 days, Sapan completes the rest of the job in 45 days. In how many days can they together do the job?
A can do a piece of work in 8 days and B can do it in 10 days seperately. How many days would it take for both A and B to finish the same work together?
24 men can do a piece of work in 17 days.How many men will be able to do it in 51 days ?
A painter can paint a fence in 24 hours. After 6 hours he takes a break. What fraction of the fence is yet to be painted?
Madhur works 2 times faster than Sagar. If Sagar can complete a job alone in 18 days, then in how many days can they together finish the job?
Pradeep has done 1/4th of a job in 14 days, Saquib completes the rest of the job in 56 days. In how many days can they together complete the job?
A can do a work in 12 days while B can do it in 15 days. They undertake to complete it together for Rs. 450. what will be the share of A in this amount of money ?
A does 60% of a work in 15 days. He then calls B, and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?