A can do a work in 12 days while B can do it in 15 days. They undertake to complete it together for Rs. 450. what will be the share of A in this amount of money ?
Rs.200
Rs.240
Rs.250
Rs.300
Correct Answer:
Rs.250
← Previous Question
Next Question→
More Questions from
Time and Work
A does 60% of a work in 15 days. He then calls B, and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 4 days. How long B alone would take to do the whole work?
A can do a work in 20 days and B in 10 days. If they work on it together for 5 days, then what fraction of work is left.
M is thrice as good as workman as N and together they finish a piece of work in 30 days. In how many days will M alone finish the work?
A can finish a work in 7 days . B can finish the same work in 9 days . The days required to finish the work by both of them together.
A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in
A and B together do a job in 15 days and A alone could do the same job in 20 days. How many days would B take to do half the job if he worked alone?
X, Y and Z can do a piece of work in 30, 40 and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?
A,B and C contract a work for Rs. 440. Together A and B are to do 9/11 of the work. The share of C should be:
A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments