A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?
30 days
50 days
40 days
60 days
Correct Answer:
40 days
← Previous Question
Next Question→
More Questions from
Time and Work
An hour-long test has 60 problems. If a student completes 30 problems in 25 minutes, then the required seconds he has taken on average for computing each of the remaining problems is
Three electronic devices make a beep after every 48 sec, 72 sec and 108 sec respectively. They beeped together at 10 a.m. The time when they will next make a beep together at the earliest is
P can do (1/4)th of work in 10 days, Q can do 40% of work in 40 days and R can do (1/3)rd of work in 13 days. Who will complete the work first?
Working 7 hours in a day, 4 men can do a piece of work in 8 days. Working 8 hours in a day, the required number of men to perform the same work in 4 days will be
The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days.
A and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest work in 14 days. A alone can complete the work in _____.
A can do a work in 21 days and B in 42 days. If they work on it together for 7 days, then what fraction of work is left?
A can paint a house in 55 days and B can do it in 66 days. Along with C, they did the job in 12 days only. Then, C alone can do the job in how many days?
A, B and C can together do a job in 9 days. C alone can do the job in 36 days. In how many days can A and B do 50% of the job working together?
Working alone A can do the task in 27 hours and B can do it in 54 hours. Find C's share (in Rs) if A, B and C get paid Rs 4,320 for completing a task in 12 hours on which they worked together.