Home » Aptitude » Time and Work

P can do (1/4)th of work in 10 days, Q can do 40% of work in 40 days and R can do (1/3)rd of work in 13 days. Who will complete the work first?

Correct Answer: R

← Previous Question Next Question→

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion