Difficulty: Easy
Correct Answer: 6 days
Explanation:
Given data
Concept / Approach
Step-by-step calculation
Daily rate = (5/8) ÷ 10 = 1/16 of the job per dayTime for remaining 3/8 = (3/8) ÷ (1/16) = (3/8) × 16 = 6
Quick check
Total time = 10 + 6 = 16 days → 16 × (1/16) = 1 job.
Final Answer
6 days