Difficulty: Easy
Correct Answer: 13 days
Explanation:
Concept / Approach
Step-by-step calculation
Total work (person-hours) = 39 × 5 × 12 = 2340Daily capacity with 30 persons at 6 h/day = 30 × 6 = 180 person-hours/dayDays required = 2340 ÷ 180 = 13
Verification
13 × 180 = 2340 person-hours, equal to the original work.
Final Answer
13 days