36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?

Correct Answer: 24

Explanation:

Let the required number of days be x

Less men, More days (Indirect Proportion)


∴ 27 : 36 :: 18 : x    ⟺    27 x x = 36 x 18



x = 36 x 18
27


x = 24.