Difficulty: Easy
Correct Answer: 12 hours/day
Explanation:
Given data
Concept / Approach
Step-by-step calculation
Total pump-hours needed = 3 × 8 × 2 = 48 pump-hoursLet required hours/day for 4 pumps be H. Then 4 × H × 1 = 48H = 48 ÷ 4 = 12 hours/day
Verification
4 pumps × 12 h = 48 pump-hours, same as original requirement.
Common pitfalls
Final Answer
12 hours/day