Difficulty: Easy
Correct Answer: 18 days
Explanation:
Introduction / Context:
When identical jobs are repeated and the worker’s rate remains constant, total time scales linearly with the number of jobs. Here, “three jobs” means three times the original amount of work at the same pace.
Given Data / Assumptions:
Concept / Approach:
Total time for k identical jobs at the same rate = k * (time for one job). Thus, multiply the single-job duration by 3.
Step-by-Step Solution:
Time for 1 job = 6 days. Time for 3 jobs = 3 * 6 = 18 days.
Verification / Alternative check:
Rate-based view: Aarti’s rate = 1/6 job/day. To complete 3 jobs, needed days = 3 / (1/6) = 18 days.
Why Other Options Are Wrong:
21 days assumes slower rate; 3 and 6 days ignore the scaling by three.
Common Pitfalls:
Confusing “three times the work” with “three workers.” The scenario keeps the same worker and rate, so time multiplies by 3.
Final Answer:
18 days
Discussion & Comments