Difficulty: Easy
Correct Answer: 4 days
Explanation:
Introduction / Context: Classic combined-work calculation: sum individual daily rates to get the team rate, then invert to find the total time needed when both work simultaneously without interruptions or interference.
Given Data / Assumptions:
Concept / Approach: Team rate = 1/6 + 1/12 = 1/4 job/day. Total time = 1 ÷ team rate = 4 days.
Step-by-Step Solution: 1/6 + 1/12 = 2/12 + 1/12 = 3/12 = 1/4. Time = 1 / (1/4) = 4 days.
Verification / Alternative check: As a reasonableness check, the combined time (4) is less than the smaller of 6 and 12, which is expected.
Why Other Options Are Wrong: 6 or 9 days exceed the correct joint time; 18 is far too large for a team that includes a faster worker.
Common Pitfalls: Averaging 6 and 12 to get 9 instead of adding rates. Always add rates for combined work.
Final Answer: 4 days
Discussion & Comments