12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work?
Aptitude
Time and Work
Difficulty: Easy
Choose an option
-
A28
-
B36
-
C48
-
D52
Answer
Correct Answer: 36
Explanation
### Concept & Formula
This is a direct application of the fundamental inverse proportion rule (Chain Rule) between the number of workers and the time taken to complete a constant amount of work:
$$ M_1 \times D_1 = M_2 \times D_2 $$
### Step-by-Step Solution
1. **Identify the variables:**
$M_1 = 12$ men
$D_1 = 24$ days
$M_2 = 8$ men
$D_2 = ?$
2. **Apply the formula:**
$$ 12 \times 24 = 8 \times D_2 $$
$$ D_2 = \frac{12 \times 24}{8} $$
$$ D_2 = 12 \times 3 = 36 $$
### Exam Strategy & Shortcut
Recognize the ratio of workers. The workforce is reduced from 12 to 8, which is a ratio of $2/3$. Time taken is inversely proportional, so multiply the original time by $3/2$. $24 \times (3/2) = 36$.
### Common Pitfall
Accidentally setting up a direct proportion (cross-multiplying) instead of an inverse proportion, which would yield an illogical answer smaller than 24.
### Final Answer
Therefore, the correct answer is **36**.