Difficulty: Easy
Correct Answer: 3 days
Explanation:
Introduction / Context:
This problem checks understanding of how work, number of workers, and time are related when the total work changes. It uses the idea of man days and is a typical chain rule situation where you adjust the number of persons and the fraction of work to compute the new time required.
Given Data / Assumptions:
Concept / Approach:
First, represent the total work in terms of man days using the original group. Then compute how many man days are needed for half of that work. Finally, divide the required man days by the new number of persons to get the time. Because work is proportional to the product of persons and days, we can use proportional reasoning to move quickly between scenarios.
Step-by-Step Solution:
Step 1: Let the original number of persons be P.Step 2: Total work in man days = P * 12.Step 3: Half of this work requires (P * 12) / 2 = 6P man days.Step 4: The new workforce is 2P persons.Step 5: Time required = required man days / number of persons = 6P / (2P) = 3 days.
Verification / Alternative check:
Observe that you are doubling the workforce but doing only half the work. Doubling workers alone would halve the time from 12 days to 6 days. Doing only half the work again halves the time from 6 days to 3 days. This reasoning also leads directly to 3 days without explicit algebra.
Why Other Options Are Wrong:
2 days would require more workers or an even smaller fraction of work. 4 or 6 days imply that the effect of more workers and less work has not been fully accounted for. 12 days ignores both changes and is just the original time for full work with the original team.
Common Pitfalls:
Final Answer:
The doubled group needs 3 days to complete half of the original work.
Discussion & Comments