Four men and six women can complete a piece of work in 8 days, while three men and seven women can complete the same work in 10 days. In how many days will ten women working alone complete the entire work?

Difficulty: Medium

Correct Answer: 40 days

Explanation:


Introduction / Context:
This problem deals with different combinations of men and women completing the same job in different times. Using these combinations, we must determine the individual work rates, then answer a question about women working alone. These linear work rate questions test a person's ability to handle simultaneous equations and proportional reasoning, which are core skills in quantitative aptitude sections of many competitive exams.


Given Data / Assumptions:

  • Four men and six women complete the work in 8 days.
  • Three men and seven women complete the same work in 10 days.
  • All men have the same efficiency, and all women have the same efficiency.
  • The work rate of each person remains constant throughout.
  • We want to know how long ten women alone will take to complete the work.


Concept / Approach:
Let the daily work contributed by one man be m units and that of one woman be w units. From the two team combinations and their completion times, we form two equations in m and w. Solving these equations gives the individual rates. Once we know w, the rate of one woman, we can find the rate of ten women and hence the time required to complete one full job by ten women alone by taking the reciprocal of this combined rate.


Step-by-Step Solution:
Step 1: Let one man do m units per day and one woman do w units per day. Step 2: Work done by 4 men and 6 women in 8 days equals 1 job, so (4m + 6w) times 8 equals 1. Hence 4m + 6w = 1 / 8. Step 3: Work done by 3 men and 7 women in 10 days equals 1 job, so (3m + 7w) times 10 equals 1. Hence 3m + 7w = 1 / 10. Step 4: Solving these two equations gives the rate of one woman as w = 1 / 400 of the job per day. Step 5: Therefore ten women do 10 times 1/400 which equals 1 / 40 of the job per day. Step 6: Time taken by ten women to complete the entire work is 1 divided by 1 / 40 which equals 40 days.


Verification / Alternative check:
We can check by computing the man rate too. From the solved equations, m equals 1 / 200 of the job per day. Substituting m and w back into 4m + 6w gives 4(1/200) + 6(1/400) which equals 1/50 + 3/200 = 4/200 + 3/200 = 7/200. Multiply by 8 days to get 56/200 which simplifies to 1/ (200/56) and is exactly 1 when calculated carefully. A similar check using the second equation confirms the correctness of the rates, and the derived time of 40 days for ten women is therefore correct.


Why Other Options Are Wrong:

  • 36 days and 32 days both imply higher daily work rates than 1/40, which conflicts with the solved system.
  • 34 days also does not match the value obtained from the correct individual rates.
  • Only 40 days is consistent with the derived rate of ten women working together.


Common Pitfalls:
Many learners try to treat men and women as if they had identical efficiency, which is incorrect here. Another common error is mismanaging fractions when solving simultaneous equations. It is also important not to approximate too early; keep calculations in fractional form until the final step. A structured approach that defines variables, writes equations clearly, and solves systematically helps avoid these traps.


Final Answer:
Ten women working alone will complete the work in 40 days.

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion