You are handling a time bound project. During the project review meeting, you find that the project is likely to get delayed due to lack of cooperation of the team members. You would

Correct Answer: look into reasons for non-cooperation

Explanation:

Looking into reasons for non-cooperation and then rectifying it the correct step. Options (c) and (d) show lack of leadership qualities. Option (a) will not solve the problem permanently. So, option (b) is correct.