Difficulty: Medium
Correct Answer: 12
Explanation:
Introduction / Context:
This question uses the standard time and work concept where total work is considered as one complete job and individual rates are added to get a combined rate. It checks the ability to convert days per job into jobs per day and manipulate fractions correctly.
Given Data / Assumptions:
Concept / Approach:
If a person finishes one job in T days, the work rate is 1/T jobs per day. When multiple people work together, their rates add. We first find the combined rate of A, B and C, then take the reciprocal to get the total time taken to finish one full job.
Step-by-Step Solution:
Rate of A = 1/72 job per day
Rate of B = 1/24 job per day
Rate of C = 1/36 job per day
Combined rate R = 1/72 + 1/24 + 1/36
Take LCM of 72, 24 and 36 which is 72
1/72 + 1/24 + 1/36 = 1/72 + 3/72 + 2/72 = 6/72
So R = 6/72 = 1/12 jobs per day
Time taken T = 1 / R = 1 / (1/12) = 12 days
Verification / Alternative check:
We can check by imagining the amount of work done in 12 days. At 1/12 job per day, in 12 days the team completes (1/12)*12 = 1 full job. This confirms that 12 days is consistent with the combined rate and completes exactly one job with no extra or missing work.
Why Other Options Are Wrong:
9 days would imply a rate of 1/9 which is greater than 1/12 and inconsistent with the calculated sum. 15 and 18 days correspond to combined rates that are too slow. 10 days also produces too large a rate. Only 12 days matches the exact sum of individual rates.
Common Pitfalls:
Typical mistakes include adding the times directly instead of adding rates, or computing the LCM incorrectly. Some students may invert the final rate incorrectly or stop at a fractional answer without simplifying. It is important to remember that time and rate are reciprocals of each other in these problems.
Final Answer:
Therefore, all three working together will finish the work in 12 days.
Discussion & Comments