Difficulty: Medium
Correct Answer: 4 1/2
Explanation:
Introduction / Context:
The statement “6 men joined to replace 2 men” implies 2 left and 6 joined, so the new team size is 12 − 2 + 6 = 16. Use total man-days and phase-wise accounting to compute the remaining time with the new team size.
Given Data / Assumptions:
Concept / Approach:
Remaining man-days divided by the new daily capacity (16) gives the remaining time.
Step-by-Step Solution:
Remaining work = 108 − 36 = 72 man-days.Days needed with 16 men = 72 / 16 = 4.5 days = 4 1/2 days.
Verification / Alternative check:
Fractional days are acceptable because the last day need not be whole; work is continuous.
Why Other Options Are Wrong:
2, 3, and 4 days are too few; 5 is too many relative to 72 man-days and 16 men.
Common Pitfalls:
Misreading “replace” as net zero change; the wording indicates 2 left and 6 joined, producing a net +4 men.
Final Answer:
4 1/2
Discussion & Comments