Difficulty: Medium
Correct Answer: 6 2/3%
Explanation:
Introduction / Context:
“A takes 4/5 as many days as B” means A is faster. We use the relationship between times and rates to find B’s per-day efficiency, expressed as a percent of one full job.
Given Data / Assumptions:
Concept / Approach:
Rates: r_A = 1/T_A and r_B = 1/T_B. Then r_A + r_B = 3/20. Substitute T_A = (4/5)T_B to solve for T_B and r_B, then convert to percent.
Step-by-Step Solution:
1/((4/5)T_B) + 1/T_B = 3/20(5/4)*(1/T_B) + 1/T_B = (9/4)*(1/T_B) = 3/201/T_B = (3/20)*(4/9) = 12/180 = 1/15 job/dayB’s efficiency = (1/15)*100% = 6 2/3%.
Verification / Alternative check:
Then A’s rate is 1/T_A = 1/((4/5)T_B) = 5/(4T_B) = 5/60 = 1/12; sum 1/12 + 1/15 = 3/20, consistent.
Why Other Options Are Wrong:
16%, 10%, 8 1/3%, and 5.55% do not match the exact 1/15 per day.
Common Pitfalls:
Interpreting “4/5 as many days” as 4/5 the rate; it refers to time, not rate.
Final Answer:
6 2/3%
Discussion & Comments