Work and Wages problems


  • 1. 
    A and B undertook to do a piece of work for $4500. A alone could do it in 8 days and B alone in 12 days. With the assistance of C they finished the work in 4 days. Then C's share of the money is:

  • Options
  • A. $2250
  • B. $1500
  • C. $750
  • D. $375
  • Discuss
  • 2. 
    A, B and C undertake to complete a piece of work for ? 1440. A alone can complete the work in 8 days, B in 12 days and C in 16 days. They complete the work with the help of D in 3 days. What does D get?

  • Options
  • A. ? 265
  • B. ? 270
  • C. ? 300
  • D. None of these
  • Discuss