Time and Work problems

  • 1. 10 boys can complete a work in 7 days and 10 girls take 14 days to complete the work. How many days will 5 boys and 10 girls take to complete the work ?

  • Options
  • A. 13 days
  • B. 10 days
  • C. 7 days
  • D. 16 days
  • Also asked in: GATE, CAT, Bank Exams, AIEEE, Bank PO, Bank Clerk

  • Discuss
  • 2. 50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?

  • Options
  • A. 36
  • B. 38
  • C. 40
  • D. 45
  • Also asked in: GATE, Bank Exams, Bank PO, Bank Clerk

  • Discuss
  • 3. Robin can do a work alone in 9 days. Amit can do the same work alone in 6 days. Both of them finish the work together and they get a total Rs 2500. What isthe share (in Rs) of Robin?

  • Options
  • A. 1700
  • B. 1200
  • C. 1500
  • D. 1000
  • Discuss
  • 4. A does 1/2 as much work as B and C does1/2as much work as A and B together. If C alone can finish the work in 40 days, then together all will finish the work in

  • Options
  • A. 30 days
  • B. 40/3 days
  • C. 15 days
  • D. 16 days
  • Also asked in: Bank Exams

  • Discuss
  • 5. If 5 person together can make 5 mats in 5 hrs, then 10 person in 10 hours will make

  • Options
  • A. 20 mats
  • B. 10 mats
  • C. 15 mats
  • D. 5 mats
  • Also asked in: Bank Exams

  • Discuss
  • 6. In a fort there was sufficient food for 200 soldiers for 31 days. After 27 days, 120 soldiers left the fort. For how many extra days will the rest of the food last for the remaining soldiers?

  • Options
  • A. 12 days
  • B. 10 days
  • C. 8 days
  • D. 6 days
  • Also asked in: Bank Exams

  • Discuss
  • 7. A labourer can do a job in 50 hours. After 5 hours he takes a break. What fraction of the job is yet to be done?

  • Options
  • A. 0.8
  • B. 0.5
  • C. 0.75
  • D. 0.9
  • Also asked in: Bank Exams

  • Discuss
  • 8. If 10 people can do a job in 20 days,then 20 people with twice the efficiency can do the same job in

  • Options
  • A. 5 days
  • B. 10 days
  • C. 20 days
  • D. 40 days
  • Also asked in: Bank Exams

  • Discuss
  • 9. A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

  • Options
  • A. 17
  • B. 19
  • C. 19.5
  • D. 21
  • Also asked in: Bank Exams

  • Discuss
  • 10. If Mr. Raghav taught a total of 500 hours, then what is the difference in number of hours of teaching algebra and modern Maths?

  • Options
  • A. 15
  • B. 20
  • C. 25
  • D. 40
  • Also asked in: Bank Exams

  • Discuss