Time and Work problems

  • 1. 
    A, Band C can do a piece of work individually in 8, 12 and 15 days, respectively. A and B start working but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed?

  • Options
  • A. 58/9 days
  • B. 46/7 days
  • C. 67/13 days
  • D. 33/4 days
  • Discuss
  • 2. 
    A and B can do a piece of work in 9 days and 18 days, respectively. As they were ill, they could do 90% and 72% of their efficiency, respectively. How many days will they take to complete the work together?

  • Options
  • A. 71/7
  • B. 8
  • C. 5
  • D. 121/2
  • Discuss
  • 3. 
    36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in this?

  • Options
  • A. 16
  • B. 18
  • C. 20
  • D. 22
  • Also asked in: Bank Exams, Bank PO

  • Discuss
  • 4. 
    It is given that 16 men working 18 h a day can build a wall 36 m long, 4 m broad and 24 m high in 20 days. How many men will be required to build a wall 64 m long, 6 m broad and 18 m high working 12 h a day in 16 days?

  • Options
  • A. 60
  • B. 20
  • C. 30
  • D. 35
  • Discuss
  • 5. 
    A men can do a piece of work in 5 days. With the help of his friend, he can do the same work in 3 days. In how many days can his friend complete the work?

  • Options
  • A. 6 days
  • B. 61/2 days
  • C. 7 days
  • D. 71/2
  • Discuss
  • 6. 
    A and B each working alone can do a work in 15 days and 25 days, respectively. They started the work together but B left after some time and A finished the remaining work in 7 days. After how many days from the start did B leave?

  • Options
  • A. 3
  • B. 5
  • C. 7
  • D. 9
  • Discuss
  • 7. 
    A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B complete the remaining work alone with C in 18 days. In how many days can C working alone complete the work?

  • Options
  • A. 12
  • B. 68
  • C. 72
  • D. 90
  • Discuss
  • 8. 
    6 men can do a piece of work in 12 days while 8 women can do the same work in 18 days. The same work can be done by 18 children in 10 days. 4 men 12 women and 20 children work together for 2 days. If only men have to complete remaining work in 1 day, then find the required number of men.

  • Options
  • A. 36
  • B. 24
  • C. 18
  • D. couldn't be determind
  • Discuss
  • 9. 
    A, B and C can do a piece of work in 18, 24 and 36 days, respectively. They work alternately, first day C, second day B and third day A, fourth day C and so on. How many days will be needed to complete the work like this way?

  • Options
  • A. 18
  • B. 20
  • C. 24
  • D. 30
  • Discuss
  • 10. 
    16 children and 24 men complete a certain work for 18 days. If each child takes twice the time taken by a man to finish the work in how many days will 24 men finish the same work?

  • Options
  • A. 12 days
  • B. 24 days
  • C. 36 days
  • D. 48 dyas
  • Discuss