Difficulty: Easy
Correct Answer: 8
Explanation:
Introduction / Context: This problem is based on the concept of man-days in time and work. It is a direct application of the inverse relationship between the number of workers and the time required, given a fixed total amount of work. We know how many days 24 villagers take, and we must find the corresponding time if 36 villagers work instead.
Given Data / Assumptions: - 24 villagers can clean the canal in 12 days. - We need the number of days required for 36 villagers to clean the same canal. - Every villager works at the same constant rate. - The total amount of cleaning work remains the same.
Concept / Approach: The total work can be measured in man-days, which is the product of the number of workers and the days they work. First, we compute the total work in man-days using the original group of villagers. Then, we divide this total man-day value by the new number of workers (36) to obtain the required time with the larger group.
Step-by-Step Solution: Step 1: Compute total work in man-days using the initial scenario. Step 2: Total work = 24 villagers * 12 days = 288 man-days. Step 3: When 36 villagers work, let the required number of days be D. Step 4: Then 36 * D = 288 man-days, because total work remains the same. Step 5: Solve for D: D = 288 / 36 = 8 days.
Verification / Alternative check: We can verify this by using proportional reasoning. Time is inversely proportional to the number of workers when work is fixed. So required days = 12 * (24 / 36) = 12 * (2 / 3) = 8 days. This matches the man-day method and confirms that the answer is correct and consistent.
Why Other Options Are Wrong: - 18 and 16 days: These are greater than the original 12 days, which does not make sense because more workers should reduce, not increase, the time required. - 72 days: This is far too large and corresponds to a misunderstanding of the relationship between workers and time. - 6 days: This would require even more total man-days than available or a higher per-worker efficiency than given by the data.
Common Pitfalls: A frequent mistake is failing to use the man-day concept and simply guessing based on rough intuition. Some learners also incorrectly treat the relationship as directly proportional instead of inversely proportional. Always remember that for a fixed job, doubling the number of workers roughly halves the time, provided all other conditions remain the same.
Final Answer: 36 villagers can clean the canal in 8 days.
Discussion & Comments