Home » Aptitude » Time and Work

25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days the women stopped working. 25 men complete the remaining work in 6 days. how many days will it take for completing the entire job if only 15 women are put on the job?

Correct Answer: None of these

Explanation:

25 men and 15 women can complete, a piece of work in 12 days.
∴ Work done by them in 8 days = 8/12 = 2/3
Remaining work is completed by 25 men in 6 days
∴ Time taken by 25 men to complete the whole work = 3 x 6 = 18 days
From the question
Time taken by 15 women to complete the whole work = 1 / (1/12 - 1/18)
= 1 / {(3 - 2) / 36} = 36/(3 - 2) = 36 days


← Previous Question Next Question→

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion