  • 40 men can build a wall 200 m long in 12 days, working 8h a day. What will be the number of days that 30 men will take to built a similar wall 300 m long, working 6h per days.


  • Options
  • A. 32
  • B. 18
  • C. 36
  • D. 9

  • Correct Answer
  • 32 

    Explanation

    Given, M1 = 40, W1 = 200, T1 = 8, D1 = 12,
    M2 = 30, W2 = 300, T2 = 6 and D2 = ?
    Then, using formula
    M1T1D1W2 = M2T2D2W1
    ? 40 x 8 x 12 x 300 = 30 x 6 x D2 x 200
    ? D2 = (40 x 8 x 12 x 300)/(30 x 6 x 200) = 32 days.


  • Time and Work problems


    Search Results


    • 1. 
      20 men can cut 30 tree in 4 h. If 4 men leave the job, how many trees will be cut in 12 h?

    • Options
    • A. 72
    • B. 80
    • C. 68
    • D. 79
    • Discuss
    • 2. 
      12 men can do a piece of work in 24 days. How many days are needed to go complete the work, if 8 men do this work?

    • Options
    • A. 28
    • B. 36
    • C. 48
    • D. 52
    • Discuss
    • 3. 
      20 women can complete apiece of work in 7 day. If 8 more women are put on the job. In how many days will they complete the work?

    • Options
    • A. 4.5 days
    • B. 5 days
    • C. 5.5 days
    • D. 4.5 days
    • Discuss
    • 4. 
      A and B can do a piece of work in 60 days and 75 days, respectively. Both begin together but after a certain time A leaves off. In such case B finishes the remaining work in 30 days. After how many days did A leave?

    • Options
    • A. 25 days
    • B. 21 days
    • C. 20 days
    • D. 24 days
    • Discuss
    • 5. 
      P and Q can finish a work in 30 days, They work at it for 10 days and then Q left. The remaining work is done by P alone in 20 more days. How long will P take to finish the work alone?

    • Options
    • A. 30 days
    • B. 20 days
    • C. 60 days
    • D. 50 days
    • Discuss
    • 6. 
      If m men working m h per day, can do m units of work in m days, then n men working n h per day would be able to complete how units of work in days?

    • Options
    • A. n3/m2
    • B. m3/n2
    • C. m4/n2
    • D. n4/m3
    • Discuss
    • 7. 
      20 men complete one-third of a work in 20 days. How many more men should be employed to finished the rest of work in 25 more days.?

    • Options
    • A. 15
    • B. 12
    • C. 18
    • D. 25
    • Discuss
    • 8. 
      45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to the employed will be?

    • Options
    • A. 50
    • B. 54
    • C. 60
    • D. 72
    • Discuss
    • 9. 
      If 3 men or 4 women can built a wall in 43 days, in how many days can 7 men and 5 women build this wall?

    • Options
    • A. 16 days
    • B. 25 days
    • C. 21 days
    • D. 12 days
    • Discuss
    • 10. 
      A and B can do a piece of work in 18 days. B and C in 24 days, C and A in 36 days. Find the time in which A, B and C working together can finish the work.

    • Options
    • A. 8
    • B. 16
    • C. 24
    • D. 36
    • Discuss


    Comments

    There are no comments.

Enter a new Comment