  • Question
  • 'A' can do a piece of work in x days and B can do the same work 3x days. To finish the work together they take 12 days. What is the value of x?


  • Options
  • A. 8
  • B. 10
  • C. 12
  • D. 16

  • Correct Answer
  • 16 

    Explanation

    A's 1 day's work A = 1/x
    B's 1 day's work B = 1/3x
    (A + B)'s 1 day's work = (1/x) + (1/3x) = 4/3x
    And given one day work of both A and B = 1/12
    ? 4/3x = 1/12
    ? 3x = 48
    ? x =16


  • Time and Work problems


    Search Results


    • 1. 
      If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in?

    • Options
    • A. 2 days
    • B. 4 days
    • C. 6 days
    • D. 16 days
    • Discuss
    • 2. 
      A and B can do a piece of work in 6 and 12 days, respectively. They (both) will complete the work in how many days?

    • Options
    • A. 9 days
    • B. 18 days
    • C. 6 days
    • D. 4 days
    • Discuss
    • 3. 
      Aarti can do a piece of work in 6 days. In how many days will she complete three time of work of same type?

    • Options
    • A. 18 days
    • B. 21 days
    • C. 3 days
    • D. 6 days
    • Discuss
    • 4. 
      A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in?

    • Options
    • A. 15 days
    • B. 18 days
    • C. 20 days
    • D. 25 days
    • Discuss
    • 5. 
      A can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?

    • Options
    • A. 1/6
    • B. 1/9
    • C. 2/5
    • D. 2/7
    • Discuss
    • 6. 
      X can completed a job in 12 days. If X and Y work together, they can complete the job in 6 2/ 3 days, Y alone can complete the job in

    • Options
    • A. 10 days
    • B. 12 days
    • C. 15 days
    • D. 18 days
    • Discuss
    • 7. 
      10 men can make a wall in 8 days. How many men required to complete the same work in half days?

    • Options
    • A. 80
    • B. 100
    • C. 120
    • D. 160
    • Discuss
    • 8. 
      3 men can do a piece of work in 6 days. 5 women can do the same work in 18 days. If 4 men and 10 women work together, then how long will it take to finish the work?

    • Options
    • A. 3 days
    • B. 5 days
    • C. 2 days
    • D. 4 days
    • Discuss
    • 9. 
      3 men can do a piece of work in 18 days. 6 children can also do that work in 18 days. 4 men and 4 children together will finish the work in how many days?

    • Options
    • A. 10
    • B. 6
    • C. 12
    • D. 9
    • Discuss
    • 10. 
      P can do piece of work in 12 days, while Q alone can finish it in 8 days. With the help of R, they can finish the work in 4 days. How long will R take to finish the work alone?

    • Options
    • A. 25 days
    • B. 34 days
    • C. 14 days
    • D. 24 days
    • Discuss