A. it represents a situation where extra resources are available and the completion of project is not delayed
B. it represents that a programme falls behind schedule and additional resources are required to complete the project in time
C. the activity is critical and any delay in its performance will delay the completion of whole project
D. any one of the above
Correct Answer
it represents a situation where extra resources are available and the completion of project is not delayed