  • Question
  • Which transaction shows the most up to date planning data? A. Stock Requirement list B. MRP list C. Stock Overview report D. List display of material and accounting documents


  • Correct Answer
  • : A 


  • More questions

    • 1. Why do you need common fields in a Database?
    • Discuss
    • 2. Insert command falls in which sub-language of SQL ?

    • Options
    • A. DCL
    • B. DQL
    • C. DML
    • D. DDL
    • Discuss
    • 3. How many joining conditions are required to join 4 tables in SQL?

    • Options
    • A. 1
    • B. 2
    • C. 3
    • D. 4
    • Discuss
    • 4. What command would you use to create a backup control file?
    • Discuss
    • 5. The SQL keyword BETWEEN is used:

    • Options
    • A. for ranges
    • B. as a wildcard
    • C. to limit the columns displayed
    • D. All the above
    • Discuss
    • 6. Sensitivity analysis is used to

    • Options
    • A. identify the risks which have the largest potential impact on the project.
    • B. determine which risks are most troubling to the customer.
    • C. identify hidden requirements that were not recognized at the outset of the project.
    • D. determine which requirements will add the greatest customer satisfaction for the least effort.
    • Discuss
    • 7. Report Performance is a member of which process group?

    • Options
    • A. Controlling
    • B. Planning
    • C. Executing
    • D. Closing
    • Discuss
    • 8. A quality audit is

    • Options
    • A. a structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures.
    • B. the process of regularly evaluating overall project performance to provide confidence that the project will satisfy relevant quality standards.
    • C. an approach where the team members meet regularly to improve the process of quality control on their project.
    • D. the process of determining the appropriate actions to increase the effectiveness and efficiency of the project to provide added benefits to project stakeholders.
    • Discuss
    • 9. Executing Process Group What are the Project Management Processes included in the Executing Process Group?
    • Discuss
    • 10. Monitoring and Controlling Process Group What are the Project Management Processes included in Monitoring and Controlling Process Group?
    • Discuss