Answer A is incorrect because the WBS hierarchy does not prevent duplication by itself. Answer C is incorrect because a WBS is focused on deliverables and components or work packages and not on tasks. Answer D is incorrect because a WBS can be sized appropriately to the project size with as many levels as necessary.