logo

CuriousTab

CuriousTab

Discussion


Home Certification PMP Certification Comments

  • Question
  • Decomposing tasks into smaller activities can be helpful in reducing the amount of stress associated with overwhelmingly large milestones. What is a feature of the hierarchical nature of the WBS?


  • Options
  • A. A WBS hierarchy prevents duplication
  • B. A WBS cab be rolled up or collapsed to provide information at the appropriate level for a particular audience.
  • C. The decomposition of tasks provides a detailed planning tool
  • D. The depth of a WBS is restricted to three levels, which avoids overplanning

  • Correct Answer
  • A WBS cab be rolled up or collapsed to provide information at the appropriate level for a particular audience. 

    Explanation

    Answer A is incorrect because the WBS hierarchy does not prevent duplication by itself. Answer C is incorrect because a WBS is focused on deliverables and components or work packages and not on tasks. Answer D is incorrect because a WBS can be sized appropriately to the project size with as many levels as necessary.


  • PMP Certification problems


    Search Results


    • 1. Your company has a policy of having every software project reviewed and approved by the Architecture Review Board prior to the construction phase of a project. you are currently in the process of activity sequencing. This is a example of what?

    • Options
    • A. Gatekeeping
    • B. Milestone
    • C. New scope for the project
    • D. Project integration
    • Discuss
    • 2. A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

    • Options
    • A. Project integration plan.
    • B. WBS development plan.
    • C. Configuration management plan.
    • D. Scope management plan.
    • Discuss
    • 3. The organizational form in which the project manager has informal authority over team members and little or no input to team member?s performance appraisal is called

    • Options
    • A. weak matrix.
    • B. functional.
    • C. strong matrix.
    • D. composite.
    • Discuss
    • 4. 4 phases of project management are
    • Discuss
    • 5. An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?

    • Options
    • A. Additional resources using the contingency fund
    • B. Escalation approval to use contingency funding
    • C. Team overtime to meet schedule
    • D. Corrective action based on causes
    • Discuss
    • 6. The project manager develops a process improvement plan to encourage continuous process improvement during the life of the project. Which of the following is a valid tool or technique to assist the project manager to assure the success of the process improvement plan?

    • Options
    • A. Change control system
    • B. Process analysis
    • C. Benchmarking
    • D. Configuration management system
    • Discuss
    • 7. Sensitivity analysis is used to

    • Options
    • A. identify the risks which have the largest potential impact on the project.
    • B. determine which risks are most troubling to the customer.
    • C. identify hidden requirements that were not recognized at the outset of the project.
    • D. determine which requirements will add the greatest customer satisfaction for the least effort.
    • Discuss
    • 8. Project Integration Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Monitor and Control Project Work phase?
    • Discuss
    • 9. Ambiguous jurisdiction is more common in a functional or weak matrix organization than a strong matrix or projectized organization. Why?

    • Options
    • A. Projectized organizations tend to be large in size
    • B. Conflict between a functional manager and a project manager is more common in a functional or weak matrix
    • C. Legal issues are more frequent in a functional or weak matrix organization
    • D. Projectized and strong matrix organizations are the best companies for a project manager to work for due to less ambiguity in scope development.
    • Discuss
    • 10. Integration is primarily concerned with

    • Options
    • A. ensuring that the time, scope and cost baselines are consistent with an acceptable quality standard and with the customer?s expectations.
    • B. getting people working together effectively toward common project goals through appropriate training, management and leadership.
    • C. effectively integrating the processes among the project management process groups that are required to accomplish project objectives with an organization?s defined procedures.
    • D. ensuring that all the tools and techniques of the various planning processes are appropriately scaled to the complexity and risk exposure of the project.
    • Discuss


    Comments

    There are no comments.

Enter a new Comment