  • Question
  • The organizational form in which the project manager has informal authority over team members and little or no input to team member?s performance appraisal is called


  • Options
  • A. weak matrix.
  • B. functional.
  • C. strong matrix.
  • D. composite.

  • Correct Answer
  • weak matrix. 

    Explanation

    ?Weak matrices maintain many of the characteristics of a functional organization, and the project manager role is more that of a coordinator or expediter than that of a true project manager.?


  • PMP Certification problems


    Search Results


    • 1. 4 phases of project management are
    • Discuss
    • 2. An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?

    • Options
    • A. Additional resources using the contingency fund
    • B. Escalation approval to use contingency funding
    • C. Team overtime to meet schedule
    • D. Corrective action based on causes
    • Discuss
    • 3. What is the Purpose of a Project Charter?
    • Discuss
    • 4. Importance of project life cycle?
    • Discuss
    • 5. An important tool for project scope management is

    • Options
    • A. Fast tracking
    • B. Work breakdown structure
    • C. Crashing
    • D. A Gantt Chart
    • Discuss
    • 6. A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

    • Options
    • A. Project integration plan.
    • B. WBS development plan.
    • C. Configuration management plan.
    • D. Scope management plan.
    • Discuss
    • 7. Your company has a policy of having every software project reviewed and approved by the Architecture Review Board prior to the construction phase of a project. you are currently in the process of activity sequencing. This is a example of what?

    • Options
    • A. Gatekeeping
    • B. Milestone
    • C. New scope for the project
    • D. Project integration
    • Discuss
    • 8. Decomposing tasks into smaller activities can be helpful in reducing the amount of stress associated with overwhelmingly large milestones. What is a feature of the hierarchical nature of the WBS?

    • Options
    • A. A WBS hierarchy prevents duplication
    • B. A WBS cab be rolled up or collapsed to provide information at the appropriate level for a particular audience.
    • C. The decomposition of tasks provides a detailed planning tool
    • D. The depth of a WBS is restricted to three levels, which avoids overplanning
    • Discuss
    • 9. The project manager develops a process improvement plan to encourage continuous process improvement during the life of the project. Which of the following is a valid tool or technique to assist the project manager to assure the success of the process improvement plan?

    • Options
    • A. Change control system
    • B. Process analysis
    • C. Benchmarking
    • D. Configuration management system
    • Discuss
    • 10. Sensitivity analysis is used to

    • Options
    • A. identify the risks which have the largest potential impact on the project.
    • B. determine which risks are most troubling to the customer.
    • C. identify hidden requirements that were not recognized at the outset of the project.
    • D. determine which requirements will add the greatest customer satisfaction for the least effort.
    • Discuss