  • Question
  • An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?


  • Options
  • A. Additional resources using the contingency fund
  • B. Escalation approval to use contingency funding
  • C. Team overtime to meet schedule
  • D. Corrective action based on causes

  • Correct Answer
  • Corrective action based on causes 


  • PMP Certification problems


    Search Results


    • 1. What is the Purpose of a Project Charter?
    • Discuss
    • 2. Importance of project life cycle?
    • Discuss
    • 3. An important tool for project scope management is

    • Options
    • A. Fast tracking
    • B. Work breakdown structure
    • C. Crashing
    • D. A Gantt Chart
    • Discuss
    • 4. The project manager meets with the project team to review lessons learned from previous projects. In what activity is the team involved?

    • Options
    • A. Performance management
    • B. Scope identification
    • C. Risk identification
    • D. Project team status meeting
    • Discuss
    • 5. Typically not referred to as a buffer type in critical chain project management is ______.

    • Options
    • A. Free Buffer
    • B. Resource Buffer
    • C. Project Buffer
    • D. Feeding Buffer
    • Discuss
    • 6. 4 phases of project management are
    • Discuss
    • 7. The organizational form in which the project manager has informal authority over team members and little or no input to team member?s performance appraisal is called

    • Options
    • A. weak matrix.
    • B. functional.
    • C. strong matrix.
    • D. composite.
    • Discuss
    • 8. A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

    • Options
    • A. Project integration plan.
    • B. WBS development plan.
    • C. Configuration management plan.
    • D. Scope management plan.
    • Discuss
    • 9. Your company has a policy of having every software project reviewed and approved by the Architecture Review Board prior to the construction phase of a project. you are currently in the process of activity sequencing. This is a example of what?

    • Options
    • A. Gatekeeping
    • B. Milestone
    • C. New scope for the project
    • D. Project integration
    • Discuss
    • 10. Decomposing tasks into smaller activities can be helpful in reducing the amount of stress associated with overwhelmingly large milestones. What is a feature of the hierarchical nature of the WBS?

    • Options
    • A. A WBS hierarchy prevents duplication
    • B. A WBS cab be rolled up or collapsed to provide information at the appropriate level for a particular audience.
    • C. The decomposition of tasks provides a detailed planning tool
    • D. The depth of a WBS is restricted to three levels, which avoids overplanning
    • Discuss