Given X can do in 10 days
=> 1 day work of X = 1/10
Y can do in 15 days
=> 1 day work of Y = 1/15
1day work of (X + Y) = 1/10 + 1/15 = 1/6
Given they are hired for 5 days
=> 5 days work of (X + Y) = 5 x 1/6 = 5/6
Therefore, Unfinished work = 1 - 5/6 = 1/6
Let Q complete that work in 'L' days
=>
=>
L = 25 days.
We know that Time is inversely proportional to Efficiency
Here given time ratio of P & P+Q as
P/P+Q = 150/100 = 3:2
Efficiency ratio of P & Q as
P:Q = 2:1 ....(1)
Given Efficiency ratio of Q & R as
Q:R = 3:1 ....(2)
From (1) & (2), we get
P:Q:R = 6:3:1
P alone can finish the work in
22.5(3+1)/6 = 15 days.
From the given data,
Day Capacity
A -> 12 2
B -> 8 3 2
A + B + C -> 2 12
=> Capacity of C = 12 - 5 = 7
Ratio of capacity of A : B : C = 2 : 3 : 7
Difference of wages of C & B = 4/5 x 1540
= 4 x 308 = Rs. 1232
Now, Total work = LCM(16, 8) = 48
A's one day work = + 48/16 = + 3
B's one day work = - 48/8 = -6
Given A worked for 5 days to build the wall => 5 days work = 5 x 3 = + 15
2days B joined with A in working = 2(3 - 6) = - 6
Remaining Work of building wall = 48 - (15 - 6) = 39
Now this remaining work will be done by A in = 39/3 = 13 days.
Total work = 100+50 = 150man-days
In 8 days 100 man-days work has been completed. Now on 9th and 10th day there will be 25 workers. So in 2 days they wll complete additional 50 man- days work. Thus the work requires 2 more days.
Given (3 Men + 4 Women + 6 Children) -----> 9 days
But W = 2M and C = M/2
Now, convert Men and Children into Women by
Therefore, 7 women alone can complete this work in 9 days.
Remaining work = 1 - 9/10 = 1/10
=> A & B together completes 1/10 of work in 4 days
=> 1 work can completed in ------ ? days
Let it be x days
=>
=> x = 40 days.
Hence, A & B together can complete the work in 40 days.
(20 x 18) men can complete the work in in one day.
one man's one day work = 1/360
(18 x 15) women can complete the work in 1 day
1 woman's one day work = 1/270
So, required ratio = = 4:3
(16M + 12W) x 20 = 18W x 40
=> 2M = 3W
Then,
Convert all men into women
12M + 27W = 27 + 12 x 3/2W = 45W
Let number of days required be 'D'
=> 18 x 40 = 45 x D
=> D = 16 days.
Rate of leakage = 8.33% per hour
Net efficiency = 50 - (16.66 + 8.33)= 25%
Time required = 100/25 = 4 hours
Comments
There are no comments.Copyright ©CuriousTab. All rights reserved.