The latest time that the event can be delayed without delaying the completion of the entire project in PERT chart is:
earliest allowable time
latest allowable time
earliest pass
latest pass
None of the above
Correct Answer:
latest allowable time
← Previous Question
Next Question→
More Questions from
Management Information Systems
The study project proposal
Data are allowed to be transmitted in only one direction in a:
Which of the following is(are) true of an artificial intelligence system?
The order entry subsystem creates a file of order records that are input to the
To be successful in implementing DSS, organizations should have the following characteristics except:
The amount of a certain product sold to a certain customer in a past period can be obtained from the
Environmental information has greater value on the
Customer data (name and address, shipping instructions, credit terms, etc.) is provided by the:
Many large organizations have information _____ where managers can use fourth-generation languages to retrieve the facts they need from online data bases, and where staff experts are available to provide PC hardware/ software guidance.
The prime concern of financial control is
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments