Home » Aptitude » Time and Work

P and Q can complete a task in 50 and 20 days respectively. In how many days can they complete 70% of the task if they work together?

Correct Answer: 10 days

← Previous Question Next Question→

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion