Portion of work completed by one man in 11/2 days.
i.e., 3/2 days = 3/(2 x 3) = 1/2
Portion of work completed by one women in 11/2 days.
i.e., 3/2 days = 3/(2 x 4) = 3/8
∴ Portion of work completed by boys = 1 - (1/2 + 3/8) = 1/8
Now, portion of work completed by each boy in 3/2 days = 3/(2 x 12) = 1/8
Hence, only one boys would be required.