A and B separately can complete a work in 6 days and 3 days respectively. If they work together, then in how many days will they complete the work?

Correct Answer: 2 days

Explanation:

Work completed by A + B in one day = 1/6 + 1/3 = 1/2
∴ Time taken by A + B to complete the work = 2 days.